Entering supply connection points into the water supply system

Under “Installation” in the “Water Systems” tab, in the “Water supply” group of the main toolbar, there is an option for entering the supply connection points of the water supply system:

Supply connection point

Enters the supply connection points of the water supply system.

The following parameters can be configured when entering or editing a supply connection point. Some parameters only appear if the “Simplified entry” option in “Design options” under “General options” is deactivated:

  • Reference
    Element reference. This value can be locked or unlocked. The program will create or modify the reference when updating results if unlocked.
  • Supply connection reference
    The type of supply connection point can be selected by reference. These types can be created and edited from "Design and check options to be carried out" in "General options", in the "Project" group.
  • General data
    The element's general data can be defined. Some of these values can be locked or unlocked. If a value is locked when updating the results, it is not modified and remains unchanged.
    • Temperature (Lock/Unlock)
    • Flow (Lock/Unlock)
    • Pressure (Lock/Unlock)
  • Public network (optional)
    Indicates that the connection is to a public network. In this way, the available flow and pressure can be entered:
    • Flow
    • Pressure
  • 3D layout
    The position and angle of the element can be defined. This section only appears when editing a previously entered element.
    • Position (x, y, z)
    • Angle
  • Label (optional)
    The information visible in the element's label can be managed.
    • Reference (optional)
  • Bill of quantities
    The element's bill of quantities generation can be controlled by filters.
    • Supply connection point
  • Checks
    The checks carried out on the element can be consulted and listed. The program will check that the flow and pressure data entered in the “Public network” section are enough to cover the values defined in the "General data" section.
Note:
The “Water supply” option in the bottom right corner of the section provides access to the options for defining the elements in this section.