Share
Associated programs

Sequence of input and output of data for the energy simulation of a building

The energy simulation of a building can be carried out in the program using the following input and output sequence:

  1. Create a new job (from "File", "New").
  2. Link to BIMserver.center. The building geometry, construction systems, shadows, lighting power of spaces and the definition of some air conditioning systems can be imported from the BIM model.
  3. In the "Building" tab, the definition of the building model is completed:
    • Reviewing and defining the project’s general data (from the "General data" group), including general parameters and site data.
    • Defining the characteristics of the spaces through the management of their libraries ("Building" side tree, "Library", "Spaces").
    • (Optional) If the construction systems have not been imported, defining the characteristics of the building elements through the management of their libraries ("Building" side tree, "Library", "External walls/Partitions/Walls in contact with soil/Floors in contact with soil/Intermediate floor slabs/Roofs/Doors/Glazed openings/Skylights").
    • Edge processing (via the "Edges" option in the top toolbar) for generating and processing linear thermal bridges.
    • (Optional) Reviewing, adjusting and validating the data presented by the building model and its structure in zones, spaces and elements, own shadows and remote shadows (side tree "Building", "Zones/Own shadows/Remote shadows").
    • Entering DHW systems and air-conditioning systems (via the tools in the side tree "Building", in "Zones", "Terminal units/ DHW systems/Air-conditioning systems", or via the blocks "DHW systems" and "Air-conditioning systems" in the top toolbar).
    • Checking the building model (from "Errors", "Check the model") and correcting errors and warnings by editing the data in this tab.
  4. (Optional) Data consulting and editing elements in floor plans ("Floor plans" tab).
  5. In the "Analysis" tab, the design options are configured, the analysis is carried out and the results are viewed:
    • Setting the design options ("Analysis" group, "Design options").
    • Analysis and energy simulation of the building ("Analysis" group, "Analyse").
    • (Optional) On-screen display of the analysis results in the main display area, at building or zone level (depending on the selection in the side tree "Building").
    • Obtaining reports (using the options in the "Reports" group) and analysis files (using the options in the "Analysis" group).
  6. (Optional) Obtaining drawings (from the "Drawings" option in the "File" menu or at the top of the interface).
  7. Exporting to BIMserver.center ("BIMserver.center" group, "Share"). If an analysis of improvement measures is desired, the "Improvement measure" option is used for the export.