Grupo de contenido: Applications with a "Bill of quantities" tab
As of version 2023.b, job certifications can be registered and managed from the "Bill of quantities" tab. A job certification consists of economically quantifying the job carried out up to a given moment in accordance with the items included in the bill of quantities that has been accepted and signed between both parties. To define […]
The "Show the complete description instead of the summarised description" option has been added in the "BoQ Reports" configuration panel. When this option is checked, the text entered in the "Description" tab of its definition in the "Project database" is used as a reference for the items. Otherwise, the text entered in the "Summary" field […]
Due to the increase of available options, the way to activate or deactivate the visibility of the columns in the bill of quantities table or in the databases has been modified. For this purpose, the "Columns" button has been added in the "View" group of the toolbar in the "Bill of quantities" tab, as well […]
The "Sort tree" option has been added to the "Edit" group of the toolbar in the "Bill of quantities" tab. The option is also available in the "Project database" and "Cost databases" editing windows. This feature allows users to sort the work sections and/or items by their code and in alphabetical order.
The "Rebuild tree" feature has been added to the toolbar of the "Bill of quantities" tab in the applications where this tab is included. This button is available in the main window of the "Bill of quantities" tab, as well as in the definition panel of the cost databases and prices of the job. Thanks […]
A tool (blue arrow) has been added to search for the code of a concept in the following points: "Prices" window of the job or the "Cost databases" When entering the code of a concept. When adding a concept to the breakdown of an item. When adding a component of the waste breakdown of a […]
As of the 2021.e version, when clicking on the "Assign" option in the active cost database when editing the mapping file, the work section code will be associated to the selected element in addition to the concept code. This implementation responds to the fact that usually the work section structure of the mapping file corresponds […]
As of the 2021.e version, applications that include the "Bill of quantities" tab can obtain the waste decomposition of the project. The waste decomposition of an item is defined in the "Waste" tab associated with the concept. When adding a waste component to the decomposition, the concept code and type must be entered. Four types […]
Thanks to the implementation of environmental data in the definition of the job concepts, it is now possible to determine the value of the project’s environmental impact indicators. The unit value of the energy cost (MJ) or the CO2 emissions (kg) of a simple element is introduced using the technical information parameters of the concept. However, […]
As of the 2021.e version, it will be possible to enter certain technical parameters associated with the items and resources defined in a cost database or the prices of a project. This data will be used to determine the environmental impact indicators and the construction and demolition waste of the job. The following parameters are […]
A new column has been included in the concepts table that appears in the cost database and the prices of a project. In this column an icon will be displayed when the concept has data available on one of the following sections: Graphical information Attached documents Specifications Technical information Waste This way it is easier […]
As of the 2021.c version, users can enter the information related to the tender specifications in the prices of a project or in a cost database. Using the "Specifications" option that is contained in the "Project" group of the toolbar, users can define the codes of the sections of each specification, as well as their […]