Plugin MedBIM - Revit

Introduction

The MedBIM - Revit Plugin is a CYPE plug-in that is installed in Autodesk Revit and generates a quantity extraction file and links the Revit model to a bill of quantities from Arquimedes.

The "Bill of quantities of BIM models" module, enables the direct connection between Arquimedes and Revit, which allows users to assign to an element of the BIM model a code of an item belonging to the work section structure of Arquimedes, and to obtain the quantities for an existing bill of quantities or for a new one.

MedBIM - Revit Plugin features

  • Integration into the Revit environment through its ribbon's "Add-ons" tab.
  • Simultaneous work with Revit, Archimedes and the "Bills of quantitities of BIM models" module. Users can work with two monitors.
  • Full interaction between Revit, Arquimedes and any of its modules.
  • Reading of Revit model information (categories, families, types, specimens, system and user parameters, etc.). Tab area for conveniently selecting information associated with categories, types and specimens, rooms, materials and phases. Data sorting and filtering in columns. Location of specimens by ID and visually, highlighting and isolating them in the BIM model once located.
  • Starting from the Revit model and with the "Bills of quantitities of BIM models" module, measurement in Arquimedes on an open bill of quantities, on an existing but not open job; or creation of a new bill of quantities starting from the BIM model. New items can be added at any time.
  • Automatic assignment of items to entities of the BIM model if they contain the code of a bill of quantities item to be measured in the "Key note" parameter. The plugin can be used to have template Revit models with the entities associated with items in an Arquimedes reference database by means of the "Key note" parameter, thus reducing the subsequent manual assignment work.
  • Quantities by Revit model entities and by materials. It also allows early cost estimation by rooms, or groups of items for a specific room.
  • Assignment of several items to a type to obtain their measurements. For example, the "Basic wall" type can be assigned the items "Interior partition sheet of ceramic brick masonry for cladding", "Plaster coating" and "Plastic paint on interior walls of plaster or plasterboard".
  • Identification in the Revit model of the elements of the selected quantities lines.
  • Assigning items from the CYPE Cost Database to the Revit model. When the job units are from the CYPE Cost Database, the quantity criteria are displayed for deduction in the quantity. Revit provides quantity lines for discounting openings. If the area for discounting openings is specified based on the quantity criteria in the project, those lines that meet the criteria will be discounted. It takes into account both the deduction of openings in surfaces and the deduction of excesses.
  • Linking several jobs or several Revit projects to the same Arquimedes bill of quantities. It is common practice to have several Revit models linked to the same bill of quantities: architecture, structures and MEP systems. In this case, the Arquimedes "Consolidation of bills of quantities" module is essential, as it allows the work sections and items of the bill of quantities obtained by the CYPECAD, Detailed priced bill of quantities estimators and Budget generators programs to be combined in a single bill of quantities. This saves time and work, and minimises errors or omissions of items.
  • Automatic detection of the quantity unit when assigning an item to the BIM model element and assigning the most appropriate combination of dimensions to obtain the quantity lines per item. The combination used to obtain the quantities can be changed to a user combination. Comments for the quantity lines can also be edited.
  • Customisation of the formula to obtain the quantities. Users can change how the quantities of a specific category are calculated according to their criteria, even by using formulas.
  • With change control, identification of "Categories", "Types" and "Specimens" that have changed after extracting the quantities, and differentiation in the bill of quantities of the quantity lines from the Revit model from the user's quantity lines.
  • After exporting or extracting the quantities, the Revit license is free. The company is not obliged to have a license assigned to the person carrying out the quantities, as there is no need to work with Revit.
  • The person carrying out the quantities does not need to be familiar with Revit. With a few hours of training, you can understand what a Revit BIM model looks like and manage it with Arquimedes.
  • There is no need to carry out the quantities in Revit, as what you get is the Revit model to be able to work with it. Therefore, there is no need to be on the same network to share the central file of the project.

Direct connection between Revit and Arquimedes to obtain quantities from a BIM model

The MedBIM – Revit plugin allows you to obtain quantities from a Revit BIM model and, thanks to the "Bills of quantities of BIM models" module, incorporate them into an Arquimedes bill of quantities.

The measurement can be incorporated into a new Arquimedes bill of quantities or into an existing one (pre-designed bill of quantities). The two scenarios are presented below:

  • No prior bill of quantities exists
    The project modelled in Revit is linked to a new Arquimedes project, which, in turn, will be associated with the CYPE Cost database or with any other database that Arquimedes can read. In Arquimedes, the items representing each element modelled in Revit are introduced and linked. The measurement is generated using the information extracted from the Revit model. In this way, the bill of quantities structure in Arquimedes is gradually formed.

    If there are construction elements with keynotes that match the item codes of the associated database, these are automatically entered into the bill of quantities, linked to the corresponding construction element, and their quantities generated.
  • A prior bill of quantities exists
    The Revit project is linked to a prior bill of quantities and its items are related to each element modelled in the BIM program. This generates the measurement for each item with the information extracted from the Revit model.
    If there are construction elements with keynotes that match the code of certain items in the bill of quantities, these are automatically linked. If the keynote code does not exist in the bill of quantities but does exist in the associated database, it is automatically added to the bill of quantities, linked to the corresponding construction element, and its measurement is generated.
    Normally, the prior bill of quantities (also called the pre-designed bill of quantities) is the one used to inform the developer and obtain the property feasibility study. Once linked to the project modelled in Revit, it can be modified or completed with new items if there are elements modelled in Revit that were not foreseen in that bill of quantities; or conversely, elements present in the prior bill of quantities but not yet modelled may be modified or added in Revit. In this way, the Revit model also minimises omissions and item-related errors.

Furthermore, considering that a building project may be generated using several Revit projects (architecture, structures, services), these can be linked to the same Arquimedes bill of quantities using the Arquimedes "Consolidation of bills of quantities" module.

Obtaining the quantities from the Revit BIM model

The process of obtaining the quantities in Arquimedes from the Revit BIM model can be started in two ways, which will differ in the use of the Revit license:

Option 1: After modelling the project in Revit, a file is generated and imported from Arquimedes to extract the quantities

In this case, the Revit license is only required until this file is generated. When the file is imported from Arquimedes, the license for Arquimedes and the "Bill of quantities of BIM models" module is required. To use the CYPE Cost Database and other Arquimedes modules the corresponding licences must also be obtained.

The file is generated using the "Generate quantities extraction file" option in the Revit "Complements" tab. It will have the same name as the Revit job but with a .mcsv extension and will be created in the directory where the Revit job is located. The "Show quantities extraction file" option displays the generated files.

To import the .mcsv file from Arquimedes and extract the quantities from the Revit model, the "Import Revit quantities extraction file" option is used, which can be accessed from the "File" menu, "Connection with Revit".

More information:
More information on this option can be found in the "Options for working with the Revit model from the Arquimedes environment" section.

Option 2: After modelling in Revit, from this same program the job is linked to an Arquimedes bill of quantities to extract the quantities

In this case, the licenses for Revit, Arquimedes and the "Bills of quantities of BIM models" module must be available at the same time. To use the CYPE Cost Database and other Arquimedes modules the corresponding licenses are also required.

The "Link with Arquimedes job" option in the Revit "Complements" tab must be used. This option opens the "Link to Arquimedes" dialogue box, the options for which vary:

  • If no Arquimedes bill of quantities has been previously linked, the "Link with Arquimedes job" and "Cancel operation" will be displayed.
  • If there is already a previous link, the "Update changes carried out in Revit, in Arquimedes", "Link with Arquimedes job" and "Cancel the operation" options will be displayed.

After linking, users can work in Revit, Arquimedes and the "Assign items and quantity extraction" window simultaneously.

Both modes, initiated with the Revit options "Generate quantities extraction file" or "Link with Arquimedes job", present the dialogue box "Linking of [Revit model path]", in which an Arquimedes job is linked to another Revit job; and then the dialogue box "Assign items and quantity extraction", in which the whole process of assigning items to Revit building elements and extracting the quantities of each of them is carried out.

Linking jobs from Revit and Arquimedes

The two procedures described above in "Obtaining the quantities from the Revit BIM model" introduce the "Linking from (Revit model path)" dialogue box. In it, the Arquimedes bill of quantities to which the quantity extracted from Revit is to be transferred and the databases from which the items and work sections that do not exist in the bill of quantities are to be copied are selected. The selected bill of quantities can be:

  1. A job that is open in Arquimedes
    To do this, users select the open bill of quantities to which they are going to add the quantities from Revit.
  2. A job that exists but is not open
    Users look for the bill of quantities to which the Revit quantities are going to be incorporated from a path.

    This option and the previous one are perfect when you have a pre-design of the bill of quantities prior to the project.Ā 
  3. Create a new job
    A new bill of quantities is generated in Archimedes with the information obtained from the cost estimation made by Revit (codes of items associated to "Types") and with the help of a database associated to the bill of quantities, which includes all the necessary information for its construction (work sections, items, units, yields, prices, etc.).

This dialogue box also indicates the "Copy origin of inexistent items and work sections". This way, when the Revit job from which the quantities are extracted contains key notes with codes of items that are not defined in the Arquimedes bill of quantities, this part of the configuration establishes in which databases the items should be searched for in order to copy them to the job.

  • The first place to look will be the reference database, which should be the same as the one being used in the connection with Revit to associate codes to the building elements.
  • If it is not found there, or if the name of the reference database is simply not provided, the program can search for the items among the databases associated with the job. As the items are located, the program reconstructs the work section structure of the source database.

"Assign items and quantity extraction" dialogue box

After linking an Arquimedes estimate to a Revit project, if Arquimedes is not currently open, the CYPE plug-in in Revit opens it. Then, the "Assign items and quantity extraction" dialogue box appears. The quantities contained in the Revit model elements can be extracted using this dialogue box.

Work environment

This dialogue box is divided into two main parts, which are framed in green and blue in the image; and a third part, framed in red, which contains the quantity detail table.

  • Green part
    The green part shows the chapter and line item structure of the bill of quantities linked to the Revit model. From here users can link entities of the Revit model to bill of quantity items. This tree is updated every time there is a change in the work section structure in the "Breakdown tree" window of the Arquimedes budget linked to the Revit model.
  • Blue part
    The blue part uses tabs to display Revit model elements ("Revit entities", "Materials" and "Rooms"). From here it is possible to link budget items to Revit model entities.
  • Quantity detail table
    The lower part of the dialogue box shows the quantity detail table assigned to the selected item in the green area. As long as the item has not been linked to the entity, when hovering over the Revit entity in the blue area, the lower part will not show the detail, but the list of copies of the selected entity.

Between the "Accept" and "Cancel" command buttons in the dialogue box, there are two further buttons to "Apply" changes and to "Extract quantities".

Panel configuration

You can configure the display of the "Assignment of items and extraction of quantities" dialogue box to make it easier for the user to connect with the Revit model according to their preferences or monitor types.

To access the configuration of the link editor with Revit, you must select the "Extraction of measurements" button located in the "Breakdown tree" window in ArquĆ­medes and choose the option "Configure link editor with Revit".

You can choose between four display types:

  • Automatic
    This option is activated by default. With it, data distribution is based on the aspect ratio of the monitor being used (width Ɨ height).
  • Panoramic
  • Classic
  • Customised
    The user decides how to distribute the data.

Adding new work sections and items

In the green part, from the toolbar of the chapters area, it is possible to add a new work section to the work section structure of the bill of quantities with the "New work section" button (1). In the dialogue box that appears, filling in at least the "Code" and "Summary" fields is required.

To create a sub-work section within an existing work section, simply go to that work section and use the "New work section" option (1).

Then, a new item can be added, within a work section or sub-work section, with the "Add new item to the report" button (2) in the toolbar of the items area. From the dialogue box shown, "Selection of the concept to add to the breakdown of %s", the following is possible:

  • Add an item from an open database, using the "Search in" option.
  • Create a new line item type concept (with breakdown or lift), from the "Create new concept" option.
Nota:
A new work section or a new item can also be created in the bill of quantities in the traditional way from the Arquimedes "Breakdown tree" window. Once a work section or item is created from that window, the "Assign items and quantity extraction" dialogue box is updated to show the new work section or item. If it is not displayed, click on the "Update" button (3) of the ā€˜Line item assignment and measurement extraction’ dialogue box.

To locate a work section or a line, simply click on the "Search work section or item" button (4) on the toolbar in the chapters area. From the "Search for work section or item" dialogue box that appears, users can search for the item by:

  • Code
    By entering it in the corresponding field and pressing any of the buttons on the right.
  • Sequential location by text fragment
    By typing the complete words or only an initial part of them separated by spaces.
Buenas prƔcticas:
In case the database has a dictionary, an additional button called "Search by dictionary" shall appear next to the "Search work section or item" button (4).

Finally, the "Show in "Breakdown tree" window" button (5), located on both toolbars, is used to locate the work section or line item selected in the "Assign items and quantity extraction" dialogue box in the Arquimedes "Breakdown tree" window.

Linking Revit model entities to bill of quantity items

Quantities can be extracted or updated from the green part by linking entities in the Revit model to bill of quantities items.

In this part, below the description of the selected item, the toolbar offers the following options:

  • Add a new element to the report (1)
    Links a Revit entity from one of the tabs in the blue part to an item in the chapter tree in the green part. After selecting both the entity and the item, click this button, which will make the linked entity appear in the list below.
  • Remove selected item from the report (2)
    Removes a linked entity from the lower list.
  • Replace entity (3)
    Selects an entity already linked to an item and change it to another entity by selecting it from the entities on the tabs in the blue part.
  • Locate linked entity (4)
    Selects an entity already linked to a line item and position on it in the corresponding Revit entities tab in the blue part.
  • Show complete quantities (5)
    This enables users to visualise how the quantities would look like if they were extracted, without having to extract the quantities and leave the "Assign items and quantity extraction" dialogue box.
MÔs información:
In the dialogue box that appears ("Complete quantities of..."), the "Apply the numerical grouping defined in the column combination" option can show how the table would look with the grouped lines for those in which the grouping has been defined according to matching dimensions.

The "Group quantities lines" option complements this option for grouping quantities lines, which can be found in detail in the "Options to simplify the number of detail lines" section..

Linking bill of quantities items to entities in the Revit model

From the blue part, the quantities can be extracted or updated by linking bill of quantities items to entities in the Revit model.

In this part, just below the list of Revit model elements, the toolbar offers the following options:

  • Add new item to the report (1)
    Links an item from the chapter tree in the green part to a Revit entity from one of the upper tabs in the blue part. After selecting both the line item and the entity, this button must be clicked, which will make the linked line item appear in the list below.
  • Remove selected item from the report (2)
    Removes a linked item from the lower list.
  • Replace entity (3)
    Selects an item already linked to a Revit entity and changes it to another line item by selecting it from the line items in the green part.
  • Locate linked entity (4)
    Selects an item already linked to a Revit entity and places it on the list of items in the green part.
Note:
There are "Categories" in the Revit element tree that only have one "Type", these categories are "Areas", "Property lines" and "Topography". In these categories, the inclusion of items and obtaining the quantities is carried out in the same way as explained for the other categories, with the exception that there is only one "Type" and, therefore, there is no "Type" table.

Quantity details table

In the lower part of the "Assign items and quantity extraction" dialogue box, the quantity detail table assigned to the selected item in the green part is displayed.

  • If an item has not been linked to a Revit entity, when hovering over the Revit entity in the blue part, the lower area does not show any detail.
  • For the quantity detail to be displayed, there must be a link between the item and the Revit entity and the item must contain a recognised unit of measurement (pc, m, m2, m3, kg, etc.).

Each quantity line in the quantity table for each item corresponds to an "Instance". The "Id" column uniquely identifies them.

In the configuration area of the quantities table, the "Quantity units" section is displayed. This is obtained by reading the quantity units contained in the item linked to the Revit entity.

A combination of parameters is used to obtain the quantities from the Revit entity. The selection in the drop-down menu "Combination used" depends on the quantities units to be used. For example, to measure surfaces, combinations such as "Area" or "Length x Height" can be used; for volumes, options such as "Volume" or "Net Area x Width" can be used; and for weights, the "Density x Volume" formula can be used.

From "Combination used", a default combination can be selected or, via the icons on the right, a new one can be added, edited or deleted.

Best practice:
To measure weight, it should be done via the "Materials" tab, as the relevant data, such as density and volume, are associated with the material and not the type.
Note:
When a combination formed by square brackets with a minus sign before them appears by default in "Combination used", it is a program combination and represents the part to be discounted by openings. The asterisk (*) indicates that it is a program combination and not a user combination.

If the quantities of an item cannot be extracted directly, a suitable parameter combination must be defined. The program will display a warning with a yellow warning symbol in the quantities table.

Add a new quantity combination

You can always define a new combination using the "Add combination" button located to the right of the "Combination used" drop-down list. After pressing this button, the "Selection of parameters for obtaining the quantity" dialogue appears, consisting mainly of two tables:

  • The table on the left initially contains the parameters associated with the Revit model entity.
  • The table on the right contains the parameters used in the quantity combination.

To add new parameters to be used in the quantity combination, simply select the desired parameter in the table on the left (you may choose an existing one or create a new one), select the column where it will be applied in the table on the right, and press the ">" button.

At the bottom of the "Selection of parameters for obtaining the quantity" dialogue, the quantity detail table for the selected item is displayed. This table allows you to preview the changes introduced before accepting the combination.

To help identify the user combinations used in the extraction of quantities, there are the "Name" and "Description" fields in the "Selection of parameters for obtaining the quantity" dialogue.

More information:
The "Group" and "Accumulate" options for quantity detail lines in the "Selection of parameters for obtaining the quantity" dialogue are explained in the "Options for simplifying the number of detail lines" section.

Option for defining the "To deduct" quantity in instances

In the "Selection of parameters for obtaining the quantity" dialogue, the "To deduct" tab is included. This only appears when openings to be deducted have been defined in the Revit model. Here you can define the parameters that will be used in creating the quantity table to be deducted, and it allows rules to be included by means of logical expressions.

In this way, there are more possibilities for obtaining the quantities of the instances, taking into account, for example, the quantities to be deducted for opening reductions.

Example:

With this option it is possible to deduct openings using more than one rule. Thus, openings larger than 4 m² could be deducted in façade or partition (basic wall) quantities, and if the opening is between 2 m² and 4 m², only half of the opening would be deducted. To do this, the logical function IF(logical_expression, true_value, false_value) is entered in the column containing the identifier with the opening area. For the example given, it would appear as follows:IF(D21<2,0,IF(D21<4,D21/2,D21)).

Quantity criterion for openings

It is possible to "Deduct openings greater than" a given area from the quantity detail table using a selection box located beneath "Unit of measurement", specifying the desired area

In addition, "Quantity criterion for openings" provides access to editing the opening quantity criteria in a panel with the same name. This button is available both in the main "Assignment of items and extraction of quantities" dialogue and in the "Selection of parameters for obtaining the quantity" dialogue, and offers the following options:

  • Deduct all openings greater than a given area.
  • Deduct only the excess over a given area of openings.
    You can also deduct only the excess over a given area between two values, and the total of openings greater than a given area.
  • Deduct only a given percentage of the openings.
    For example, deduct only a portion (normally 50%) of the openings smaller than a given value, and deduct the full amount if they exceed that value.

If the assigned item comes from the CYPE Cost Database, the project quantity criterion can be seen in the green section, just below the selection of the assigned item in the items section. If the area for deducting openings is indicated according to the project quantity criterion, those lines that meet the criterion will be deducted.

Use of the same combination in links for entities of the same family

When more than one link of several types from the same family is made to the same budget item from the "Assignment of items and quantity extraction" dialogue, the "Match" column allows the same combination to be used in links for entities of that family.

It is possible to match the measurement criteria of several entity links to one item. When one of them is changed, it is applied to all the links for that item. If the project already had different criteria (measurement combinations) in the same item, the programme does not unify them; it only does so if one of them is modified.

All the entities ("Types") linked to one item will have the same measurement criteria, as they refer to the same item.

Formation of comments in quantity tables

The quantity tables in Arquimedes admit two types of comments: the "Comment" and "Comment2" columns or fields (1).

These comments can be configured using the "Edit comments" button, located both in the configuration area of the quantity detail table (2) and in the selection area for "Types", "Materials" or "Rooms" (3).

After pressing this button, the "Comment composition for the quantity table" dialogue appears. From here, the comments for the table area can be constructed (4):

  • Subtable header
  • Quantity lines
  • ā€˜To deduct’ line separator
  • ā€˜To deduct’ quantity lines

Here it is possible to view the compositions of the "Comment" and "Comment2" columns simultaneously, which allows both comments to be compared. In addition, this dialogue provides default compositions using information from the "Category", "Family" or "Type" of the instances in the quantity extraction, which facilitates the composition of comments.

Note:
When the quantity is extracted, if comments have been defined using the "Category", "Family" and "Type" information (or any combination of these), the comments take precedence in the following priority order: "Type" > "Family" > "Category"..

From the toolbar in this dialogue (5) it is possible to "Add", "Edit" or "Delete" a comment, as well as change its order of appearance (up and down blue arrows). It is also possible to add new elements of the following types:

  • Category name
  • Level name
  • Rooms (useful in the quantity extraction of floors or ceilings, doors, windows, furniture, sanitary ware, etc.)
  • Creation phase name
  • Demolition phase name
  • Text label
  • Alphanumeric parameter (such as key note, manufacturer, etc.)
  • Numerical field (such as area, volume, etc.)
  • Opening width or opening height (available only in ā€˜To deduct’ quantity lines)

If the quantities of the item are obtained by linking a material from the "Materials" sheet, the comments can be composed using information from the material category or from the material itself.

If the assignment of items is carried out from the "Rooms" sheet, the formation of comments is simplified as shown in the third image of this section.

The "Link" option in the "Comment composition for the quantity table" dialogue refers to the entity–item link (the assignment between the Revit entity and the ArquĆ­medes item). This link has a combination for extracting quantity lines and, among other things, two comment compositions (one for each comment column, "Comment" and "Comment2"). If the "Link" option is activated, it is possible to customise each of these comment compositions for that link, so that it does not affect any other link.

Entity–item links are unique. Therefore, if comments are customised for the link and the "Link" option is activated, this change affects only that specific entity–item link or assignment.

More information:
The "G", "V", "O", "^", "M" and "-" options are explained in the section "Options for simplifying the number of detail lines", within the point "Quantity groups in quantity tables originating from Revit"..

Omitting quantity for instances

It is possible to mark the instances that you do not wish to include in the quantity for a given item. This tool complements other existing tools for filtering and defining what you want to quantify.

The option to mark instances to exclude them from the quantity becomes available once a Revit element has been linked to an item and the appropriate extraction combination has been selected or created. In the quantity detail table that is generated, you can mark the instances of each line that you do not wish to quantify using a check box located at the beginning of each quantity detail line.

Options for simplifying the number of detail lines

To simplify the number of detail lines shown in the quantity tables when generating the quantity extraction from the "Assignment of items and quantity extraction" dialogue, the following processes are available:

  • Grouping detail quantity lines originating from Revit
    The grouping of detail quantity lines is carried out after assigning to the items the types corresponding to the Revit elements.

    This grouping is defined from the "Assignment of items and quantity extraction" dialogue, by creating or editing a combination (the "Add" or "Edit" buttons located to the right of the "Combination used" drop-down list). In the dialogue that opens ("Parameter selection for obtaining the quantity"), identical dimensions can be grouped or accumulated in columns "A", "B", "C", "D" or "E" by activating the values in the "Group" and "Accumulate" columns respectively.

    This operation can be carried out both in the "Quantity by instances" tab and in the "To deduct" tab.
  • Grouping quantity lines
    The "Group quantity lines" option in ArquĆ­medes (menu "View", "Configuration") complements the "Apply the numerical grouping defined in the column combination" option for grouping quantity lines originating from the Revit model extraction.

    If in the dialogue that opens ("Set of rules for grouping quantity lines") the "Apply in quantity detail tables" check box is not activated, the quantity detail lines will not be displayed grouped, even if grouping criteria have been defined.

    This dialogue allows rules to be defined for grouping the detail lines of the quantity tables (on screen, when printing, or when exporting). The grouping of quantity detail lines applies to those imported from CAD/BIM files, to those imported from BC3 files, and to those entered manually.
  • Quantity groups in quantity tables originating from Revit
    The creation of quantity groups in quantity tables originating from Revit is based on a process of sorting and classifying according to the content of the comment of the quantity lines that make up each quantity table.

    To organise and simplify the information extracted from Revit quantities, there are options accessible by pressing the "Comment composition for the quantity table" button in the selection area for "Types" or "Materials" (identified in the side image with the red number "1"), or from the configuration area for quantity tables (identified with the red number "2").
    These options are:
    • Group header (column G)
      Allows groups to be created within the quantity table; that is, to group quantity lines by comment.
    • Visible (column V)
      Allows the information in the "Content" column to be shown in the quantity table.
    • Sort (column O)
      Allows the detail lines to be sorted alphanumerically in the quantity table by comment.
    • Ascending order (column ^)
      Allows alphanumerical sorting in ascending order in the quantity table by comment. If not activated, the sorting will be in descending order, provided the "Sort" option in column "O" is activated.
    • Visible in material quantity (column M)
      When quantities are obtained by material, the formation of the comment for the quantity lines uses information provided by the material instance itself as well as by the instance that uses that material. Hence the possibility of making the material quantity visible.
    • Visible in ā€˜to deduct’ quantity lines (column -)
      When openings are quantified, the formation of the comment for the quantity lines uses information from the opening instance itself as well as from the instance containing that opening. Hence the possibility of making the opening quantity visible.

Selecting the type of quantity table

Next to the "Extract quantities" button, a drop-down menu appears that can select the type of quantities table where the quantities extraction is to be carried out.

For example, if the quantity is to be extracted for a certification table, it should be noted that quantity extractions are not cumulative, but partial (the contents of the quantity in the "Assign items and quantity extraction" window are always dumped to the quantity tables). Therefore, this table provides a partial quantity in progress and not at source. In other words, this certification has not been closed. The same happens if the quantity is extracted for the completed job table.

Licenses and related modules

CYPE programs are activated via electronic licenses which may contain one or more modules. The list of modules compatible with each program may vary depending on the product purchased and the type of license.

To consult the list of modules compatible with this program, go to "CYPE program modules".

Please note that the list of modules available in the license will depend on the product purchased.

Download any version of Arquimedes and its plugins:

Arquimedes

Plugins compatible with Arquimedes:

Connection with Allplan:

Connection with Archicad

Plugin MedBIM - Revit

Arquimedes Database Server (64-bit)

Descarga cualquier versión de CYPEDOC - Libro del edificio:

Cypedoc. Libro del edificio

Cypedoc. Llibre de l'edifici (Andorra)